McCamey's Castle Battery
ERCOT queue ID 25INR0557
McCamey's Castle Battery (25INR0557) is listed in the ERCOT interconnection queue as a 409.6 MW battery project in Upton County, TX. The filing names Robbins Switch as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of March 30, 2028. It records the screening study as complete on January 10, 2024 and the interconnection agreement as signed on March 20, 2025.
| Queue ID | 25INR0557 |
|---|---|
| Project name | McCamey's Castle Battery |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Robbins Switch |
| Point of interconnection | 76597 Robbins Switch 138 kV |
| County | Upton |
| State | TX |
| Voltage | 138 kV |
| Capacity | 409.6 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-03-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Upton, TX: 22 requests in the ERCOT queue, 18 active totaling 5,611.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Castle Storage, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2025-03-20 |
| Screening study complete | 2024-01-10 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.