Blue Creek Energy Storage (25INR0545) is listed in the ERCOT interconnection queue as a 101.2 MW battery project in Wharton County, TX. The filing names Tap DYANN_POI8 - S_LANE_B138 Ckt 60 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2028. It records the screening study as complete on January 10, 2024.

Queue ID25INR0545
Project nameBlue Creek Energy Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationTap DYANN_POI8 - S_LANE_B138 Ckt 60
Point of interconnectionTap 138kV 42985 DYANN_POI8 - 43190 S_LANE_B138 Ckt 60
CountyWharton
StateTX
Voltage138 kV
Capacity101.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityBlue Creek Energy Storage, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Screening study complete2024-01-10
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.