Substation Scout

Blue Summit Energy Storage

ERCOT queue ID 25INR0492

Queue ID25INR0492
Project nameBlue Summit Energy Storage
Status (as published)SS Completed, FIS Completed, IA
SubstationJIM TREECE
Point of interconnection61001 JIM TREECE 345kV
CountyWilbarger
StateTX
Voltage345 kV
Capacity100 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-07-31
Source datasetlarge

Additional filed fields

Interconnecting EntityNextEra Energy Interconnection Holdings, LLC
Cdr ZoneWEST
Fuel CodeOTH
Technology CodeBA
Ia Signed40961
Screening Study Complete45307
Fis Approved45785
Air PermitNot Required
Water Availability45225

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.