WOE Gyp King Wind

ERCOT queue ID 25INR0401

Queue ID25INR0401
Project nameWOE Gyp King Wind
Status (as published)SS Completed, FIS Started, No IA
SubstationTap GYP_18 – BENJ4A
Point of interconnectionTap 138kV 33798 GYP_18 – 6088 BENJ4A
CountyKing
StateTX
Voltage138 kV
Capacity304.3 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2030-08-31
Source datasetlarge

Additional filed fields

Interconnecting EntityKSK Wind Farm 1, LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Screening Study Complete45119
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.