Hinkell BESS

ERCOT queue ID 25INR0395

Queue ID25INR0395
Project nameHinkell BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationReveille
Point of interconnection8612 Reveille 138kV
CountyLa Salle
StateTX
Voltage138 kV
Capacity78.1 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-07-01
Source datasetlarge

Additional filed fields

Interconnecting EntityReveille BESS
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45247