| Queue ID | 25INR0287 |
|---|---|
| Project name | Hide Town Energy Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Union Switch |
| Point of interconnection | 18555 Union Switch 138 kV |
| County | Scurry |
| State | TX |
| Voltage | 138 kV |
| Capacity | 102.8 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2029-10-11 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Hide Town Energy Storage LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45030 |