Isaac Solar

ERCOT queue ID 25INR0232

Isaac Solar (25INR0232) is listed in the ERCOT interconnection queue as a 50.7 MW solar project in Matagorda County, TX. The filing names Conoco as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of April 15, 2027. It records the screening study as complete on February 3, 2023, the full interconnection study as approved on December 18, 2025 and the interconnection agreement as signed on October 18, 2023.

Queue ID25INR0232
Project nameIsaac Solar
Status (as published)SS Completed, FIS Completed, IA
SubstationConoco
Point of interconnection8114 Conoco 138kV
CountyMatagorda
StateTX
Voltage138 kV
Capacity50.7 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-04-15
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Matagorda, TX: 30 requests in the ERCOT queue, 23 active totaling 5,513.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityIndustrial Bravo Project LLC
CDR reporting zoneCOASTAL
Fuel codeSOL
Technology codePV
Interconnection agreement signed2023-10-18
Screening study complete2023-02-03
Full interconnection study approved2025-12-18
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.