Shadow Ranch Solar
ERCOT queue ID 25INR0207
Shadow Ranch Solar (25INR0207) is listed in the ERCOT interconnection queue as a 807.6 MW solar project in Upton County, TX. The filing names 842 King Mountain as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of June 1, 2030. It records the screening study as complete on January 12, 2023.
| Queue ID | 25INR0207 |
|---|---|
| Project name | Shadow Ranch Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | 842 King Mountain |
| Point of interconnection | 842 King Mountain 345kV |
| County | Upton |
| State | TX |
| Voltage | 345 kV |
| Capacity | 807.6 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2030-06-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Upton, TX: 22 requests in the ERCOT queue, 18 active totaling 5,611.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | LectricWind LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2023-01-12 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.