Shadow Ranch Solar

ERCOT queue ID 25INR0207

Queue ID25INR0207
Project nameShadow Ranch Solar
Status (as published)SS Completed, FIS Started, No IA
Substation842 King Mountain
Point of interconnection842 King Mountain 345kV
CountyUpton
StateTX
Voltage345 kV
Capacity807.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2030-06-01
Source datasetlarge

Additional filed fields

Interconnecting EntityLectricWind LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete44938
Water AvailabilityNot Required