Substation Scout

Piedra BESS

ERCOT queue ID 25INR0169

Queue ID25INR0169
Project namePiedra BESS
Status (as published)SS Completed, FIS Completed, IA
SubstationTap 345-kV line Navarro () – Limestone ()
Point of interconnectionTap 345-kV line Navarro (68091) – Limestone (46020)
CountyFreestone
StateTX
VoltageNot reported
Capacity103.7 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-01
Source datasetlarge

Additional filed fields

Interconnecting EntityPiedra Solar, LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Ia Signed45475
Screening Study Complete44895
Fis Approved45918
Air PermitNot Required
Water Availability45919