Substation Scout

Compadre Solar II

ERCOT queue ID 25INR0166

Compadre Solar II (25INR0166) is listed in the ERCOT interconnection queue as a 201.4 MW solar project in Hill County, TX. The filing names Tap Sam Switch – Fort Smith as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 31, 2026. It records the screening study as complete on December 13, 2022, the full interconnection study as approved on June 16, 2025 and the interconnection agreement as signed on December 24, 2024.

Queue ID25INR0166
Project nameCompadre Solar II
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Sam Switch – Fort Smith
Point of interconnectionTap 345kV 68090 Sam Switch – 3389 Fort Smith
CountyHill
StateTX
Voltage345 kV
Capacity201.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2026-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Hill, TX: 27 requests in the ERCOT queue, 23 active totaling 7,894.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityHill Solar II, LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2024-12-24
Screening study complete2022-12-13
Full interconnection study approved2025-06-16
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first