Hadrian Energy Storage (24INR0569) is listed in the ERCOT interconnection queue as a 101.2 MW battery project in Wharton County, TX. The filing names Line Tap # NEWGLF60T3_8 - # S_LANE_B138 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of December 31, 2028. It records the screening study as complete on August 11, 2023 and the full interconnection study as approved on February 12, 2025.

Queue ID24INR0569
Project nameHadrian Energy Storage
Status (as published)SS Completed, FIS Completed, No IA
SubstationLine Tap # NEWGLF60T3_8 - # S_LANE_B138
Point of interconnectionLine Tap 138kV #43012 NEWGLF60T3_8 - #43190 S_LANE_B138
CountyWharton
StateTX
Voltage138 kV
Capacity101.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityHadrian Energy Storage, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Screening study complete2023-08-11
Full interconnection study approved2025-02-12

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first