Roost Energy Storage
ERCOT queue ID 24INR0519
Roost Energy Storage (24INR0519) is listed in the ERCOT interconnection queue as a 102.4 MW battery project in Scurry County, TX. The filing names the Knapp Sub (bus# ) – Union Switch (bus# ) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 30, 2028. It records the screening study as complete on April 28, 2023.
| Queue ID | 24INR0519 |
|---|---|
| Project name | Roost Energy Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | the Knapp Sub (bus# ) – Union Switch (bus# ) |
| Point of interconnection | the Knapp Sub (bus# 1310) – Union Switch (bus# 18555) |
| County | Scurry |
| State | TX |
| Voltage | Not reported |
| Capacity | 102.4 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-09-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Scurry, TX: 23 requests in the ERCOT queue, 17 active totaling 5,057.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Bluff Creek Energy Storage LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2023-04-28 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.