Substation Scout

White Oak King Wind

ERCOT queue ID 24INR0508

Queue ID24INR0508
Project nameWhite Oak King Wind
Status (as published)SS Completed, FIS Started, No IA
SubstationGauss ( Bus # )
Point of interconnection345 kV Gauss ( Bus # 60701)
CountyKing
StateTX
Voltage345 kV
Capacity606.5 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2030-08-31
Source datasetlarge

Additional filed fields

Interconnecting EntityKSK Wind Farm 1, LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Screening Study Complete45082
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.