Hollow Branch Creek Solar
ERCOT queue ID 24INR0422
Hollow Branch Creek Solar (24INR0422) is listed in the ERCOT interconnection queue as a 460 MW solar project in Leon County, TX. The filing names Tap Jewett - Singleton as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of June 30, 2028. It records the screening study as complete on November 29, 2022 and the interconnection agreement as signed on October 22, 2024.
| Queue ID | 24INR0422 |
|---|---|
| Project name | Hollow Branch Creek Solar |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap Jewett - Singleton |
| Point of interconnection | Tap 345kV 3390 Jewett - 44645 Singleton |
| County | Leon |
| State | TX |
| Voltage | 345 kV |
| Capacity | 460 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-06-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Leon, TX: 14 requests in the ERCOT queue, 13 active totaling 6,147.5 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Hollow Branch Creek Solar LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2024-10-22 |
| Screening study complete | 2022-11-29 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.