CATHODE BESS
ERCOT queue ID 24INR0394
CATHODE BESS (24INR0394) is listed in the ERCOT interconnection queue as a 150 MW battery project in Upton County, TX. The filing names King Mountain as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2027. It records the screening study as complete on November 1, 2022.
| Queue ID | 24INR0394 |
|---|---|
| Project name | CATHODE BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | King Mountain |
| Point of interconnection | 76635 King Mountain 138kV |
| County | Upton |
| State | TX |
| Voltage | 138 kV |
| Capacity | 150 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Upton, TX: 22 requests in the ERCOT queue, 18 active totaling 5,611.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | CED Development Inc. |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2022-11-01 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.