Eldora Solar

ERCOT queue ID 24INR0337

Eldora Solar (24INR0337) is listed in the ERCOT interconnection queue as a 200.9 MW solar project in Matagorda County, TX. The filing names Tap South Texas Project – Hillje Ckt 1 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of July 2, 2028. It records the screening study as complete on September 6, 2022 and the interconnection agreement as signed on November 15, 2023.

Queue ID24INR0337
Project nameEldora Solar
Status (as published)SS Completed, FIS Started, IA
SubstationTap South Texas Project – Hillje Ckt 1
Point of interconnectionTap 345 kV 5915 South Texas Project – 44200 Hillje Ckt 1
CountyMatagorda
StateTX
Voltage345 kV
Capacity200.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-07-02
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Matagorda, TX: 30 requests in the ERCOT queue, 23 active totaling 5,513.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityEldora Energy LLC
CDR reporting zoneCOASTAL
Fuel codeSOL
Technology codePV
Interconnection agreement signed2023-11-15
Screening study complete2022-09-06
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.