Tehuacana Creek Solar
ERCOT queue ID 24INR0188
| Queue ID | 24INR0188 |
|---|---|
| Project name | Tehuacana Creek Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Big Brown – Navarro circuit |
| Point of interconnection | Tap 345kV 3381 Big Brown – 68091 Navarro circuit |
| County | Navarro |
| State | TX |
| Voltage | 345 kV |
| Capacity | 505.4 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2027-05-18 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Tehuacana Creek Solar LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 45621 |
| Screening Study Complete | 44630 |
| Fis Approved | 46189 |
| Air Permit | Not Required |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.