Slate Solar Project

ERCOT queue ID 24INR0184

Queue ID24INR0184
Project nameSlate Solar Project
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Rio Bravo - San Ygancio
Point of interconnectionTap 138kV 8646 Rio Bravo - 8985 San Ygancio
CountyZapata
StateTX
Voltage138 kV
Capacity104.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-10-30
Source datasetlarge

Additional filed fields

Interconnecting EntityIgnis TX Solar Three LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete44630
Water AvailabilityNot Required