Cumulus Grid BESS

ERCOT queue ID 24INR0178

Cumulus Grid BESS (24INR0178) is listed in the ERCOT interconnection queue as a 210.7 MW battery project in Ellis County, TX. The filing names Venus Switch Substation as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of January 1, 2028. It records the screening study as complete on April 18, 2022, the full interconnection study as approved on January 27, 2025 and the interconnection agreement as signed on June 3, 2025.

Queue ID24INR0178
Project nameCumulus Grid BESS
Status (as published)SS Completed, FIS Completed, IA
SubstationVenus Switch Substation
Point of interconnection1906 Venus Switch Substation 345kV
CountyEllis
StateTX
Voltage345 kV
Capacity210.7 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-01-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Ellis, TX: 30 requests in the ERCOT queue, 26 active totaling 5,761.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityCumulus Grid, LLC
CDR reporting zoneNORTH
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2025-06-03
Screening study complete2022-04-18
Full interconnection study approved2025-01-27
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first