Cumulus Grid BESS
ERCOT queue ID 24INR0178
Cumulus Grid BESS (24INR0178) is listed in the ERCOT interconnection queue as a 210.7 MW battery project in Ellis County, TX. The filing names Venus Switch Substation as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of January 1, 2028. It records the screening study as complete on April 18, 2022, the full interconnection study as approved on January 27, 2025 and the interconnection agreement as signed on June 3, 2025.
| Queue ID | 24INR0178 |
|---|---|
| Project name | Cumulus Grid BESS |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Venus Switch Substation |
| Point of interconnection | 1906 Venus Switch Substation 345kV |
| County | Ellis |
| State | TX |
| Voltage | 345 kV |
| Capacity | 210.7 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-01-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Ellis, TX: 30 requests in the ERCOT queue, 26 active totaling 5,761.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Cumulus Grid, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2025-06-03 |
| Screening study complete | 2022-04-18 |
| Full interconnection study approved | 2025-01-27 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.