Yaupon Storage SLF

ERCOT queue ID 24INR0169

Yaupon Storage SLF (24INR0169) is listed in the ERCOT interconnection queue as a battery request filed at 0 MW (a net change or energy-only filing) in Milam County, TX. The filing names to Tap Gibson Switch – TNP One as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of July 1, 2028. It records the screening study as complete on February 8, 2022 and the interconnection agreement as signed on September 28, 2023.

Queue ID24INR0169
Project nameYaupon Storage SLF
Status (as published)SS Completed, FIS Started, IA
Substationto Tap Gibson Switch – TNP One
Point of interconnectionto Tap 345 kV Gibson Switch (3706) – TNP One (39950)
CountyMilam
StateTX
Voltage345 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-07-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Milam, TX: 35 requests in the ERCOT queue, 30 active totaling 8,525.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityYaupon Solar, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2023-09-28
Screening study complete2022-02-08

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.