BRP Mekong BESS

ERCOT queue ID 24INR0135

Queue ID24INR0135
Project nameBRP Mekong BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap line from Twin Oak Switch (#) to TPN One Plant Switchyard (#)
Point of interconnectionTap 345 kV line from Twin Oak Switch (#3400) to TPN One Plant Switchyard (#39950)
CountyRobertson
StateTX
Voltage345 kV
Capacity409.9 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-01
Source datasetlarge

Additional filed fields

Interconnecting EntityBRP Mekong BESS LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete44636

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.