Substation Scout

Dovetail Solar 3

ERCOT queue ID 24INR0097

Dovetail Solar 3 (24INR0097) is listed in the ERCOT interconnection queue as a 666.1 MW solar project in Jack County, TX. The filing names Tap Willow Creek – THOMPRIC as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 20, 2029. It records the screening study as complete on February 8, 2022.

Queue ID24INR0097
Project nameDovetail Solar 3
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Willow Creek – THOMPRIC
Point of interconnectionTap 345kV 1421 Willow Creek – 11523 THOMPRIC
CountyJack
StateTX
Voltage345 kV
Capacity666.1 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2029-04-20
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Jack, TX: 18 requests in the ERCOT queue, 17 active totaling 7,978.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityHecate Energy Dovetail Solar Holdings LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Screening study complete2022-02-08
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.