Substation Scout

Sypert Branch Solar Project

ERCOT queue ID 24INR0070

Sypert Branch Solar Project (24INR0070) is listed in the ERCOT interconnection queue as a 261.2 MW solar project in Milam County, TX. The filing names Tap # Scooter Switch - # Bell County East Switch Ckt 2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of April 30, 2026. It records the screening study as complete on December 6, 2021, the full interconnection study as approved on October 31, 2024 and the interconnection agreement as signed on October 12, 2023.

Queue ID24INR0070
Project nameSypert Branch Solar Project
Status (as published)SS Completed, FIS Completed, IA
SubstationTap # Scooter Switch - # Bell County East Switch Ckt 2
Point of interconnectionTap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2
CountyMilam
StateTX
Voltage345 kV
Capacity261.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2026-04-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Milam, TX: 35 requests in the ERCOT queue, 30 active totaling 8,525.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySypert Branch Solar LLC
CDR reporting zoneSOUTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2023-10-12
Screening study complete2021-12-06
Full interconnection study approved2024-10-31
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first