Compadre Solar
ERCOT queue ID 24INR0023
Compadre Solar (24INR0023) is listed in the ERCOT interconnection queue as a 405.7 MW solar project in Hill County, TX. The filing names tap Sam Switch - Venus as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of October 31, 2026. It records the screening study as complete on May 28, 2021, the full interconnection study as approved on January 31, 2024 and the interconnection agreement as signed on November 12, 2022.
| Queue ID | 24INR0023 |
|---|---|
| Project name | Compadre Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | tap Sam Switch - Venus |
| Point of interconnection | tap 345kV 68090 Sam Switch - 1907 Venus |
| County | Hill |
| State | TX |
| Voltage | 345 kV |
| Capacity | 405.7 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2026-10-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Hill, TX: 27 requests in the ERCOT queue, 23 active totaling 7,894.6 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Hill Solar I, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2022-11-12 |
| Screening study complete | 2021-05-28 |
| Full interconnection study approved | 2024-01-31 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.