Cascabel Wind 2
ERCOT queue ID 23INR0561
| Queue ID | 23INR0561 |
|---|---|
| Project name | Cascabel Wind 2 |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Rapido Substation (New ETT Substation) tapping the existing Line from CENIZO7C (#) to DELSOL7C (#). |
| Point of interconnection | 345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307). |
| County | Zapata |
| State | TX |
| Voltage | 345 kV |
| Capacity | 197.8 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Vaquero Wind Energy, LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | WIN |
| Technology Code | WT |
| Ia Signed | 45800 |
| Screening Study Complete | 45086 |
| Air Permit | Not Required |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.