Substation Scout

Lamar Unit 1 Repower

ERCOT queue ID 23INR0486

Lamar Unit 1 Repower (23INR0486) is listed in the ERCOT interconnection queue as a 66 MW gas project in Lamar County, TX. The filing names Paris Switch Station as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 18, 2027. It records the screening study as complete on August 30, 2022.

Queue ID23INR0486
Project nameLamar Unit 1 Repower
Status (as published)SS Completed, FIS Started, No IA
SubstationParis Switch Station
Point of interconnection1692 Paris Switch Station 345kV
CountyLamar
StateTX
Voltage345 kV
Capacity66 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2027-12-18
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityLa Frontera Holdings, LLC
CDR reporting zoneNORTH
Fuel codeGAS
Technology codeCC
Screening study complete2022-08-30

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first