ERCOT queue ID 23INR0468

Petunia Storage Project (23INR0468) is listed in the ERCOT interconnection queue as a 231.9 MW battery project in Milam County, TX. The filing names Tap Rogers - Tin Roof Pod as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of June 30, 2028. It records the screening study as complete on June 2, 2022.

Queue ID23INR0468
Project namePetunia Storage Project
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Rogers - Tin Roof Pod
Point of interconnection138kV Tap 3675 Rogers - 3485 Tin Roof Pod
CountyMilam
StateTX
Voltage138 kV
Capacity231.9 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-06-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Milam, TX: 35 requests in the ERCOT queue, 30 active totaling 8,525.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityPetunia Storage Project LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Screening study complete2022-06-02
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first