Substation Scout

Bronze Quinta Storage

ERCOT queue ID 23INR0456

Queue ID23INR0456
Project nameBronze Quinta Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationS_MCALLN (S. McAllen Substation)
Point of interconnectionS_MCALLN 8371 (S. McAllen 138kV Substation)
CountyHidalgo
StateTX
Voltage138 kV
Capacity103.5 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-01-01
Source datasetlarge

Additional filed fields

Interconnecting EntityKCE TX 28, LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete44662
Air PermitNot Required