Coneflower Storage Project

ERCOT queue ID 23INR0425

Coneflower Storage Project (23INR0425) is listed in the ERCOT interconnection queue as a 170.9 MW battery project in Chambers County, TX. The filing names JORDON as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of February 28, 2028. It records the screening study as complete on March 11, 2022, the full interconnection study as approved on March 19, 2026 and the interconnection agreement as signed on March 25, 2024.

Queue ID23INR0425
Project nameConeflower Storage Project
Status (as published)SS Completed, FIS Completed, IA
SubstationJORDON
Point of interconnection40855 JORDON 138 kV
CountyChambers
StateTX
Voltage138 kV
Capacity170.9 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-02-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Chambers, TX: 3 requests in the ERCOT queue, 2 active totaling 867.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityConeflower Storage Project LLC
CDR reporting zoneHOUSTON
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2024-03-25
Screening study complete2022-03-11
Full interconnection study approved2026-03-19
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first