Substation Scout

Lumberjack Storage

ERCOT queue ID 23INR0324

Queue ID23INR0324
Project nameLumberjack Storage
Status (as published)SS Completed, FIS Started, IA
SubstationTap Stryker Creek - Troup
Point of interconnection138 kV Tap 3110 Stryker Creek - 3147 Troup
CountyCherokee
StateTX
Voltage138 kV
Capacity50.9 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-11-01
Source datasetlarge

Additional filed fields

Interconnecting EntityEDP Renewables North America LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Ia Signed45371
Screening Study Complete44498
Air PermitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.