Substation Scout

Poco Trail Solar

ERCOT queue ID 23INR0273

Queue ID23INR0273
Project namePoco Trail Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Riley - Bowman Byrd Road Switch
Point of interconnectionTap 345kV 6101 Riley - 1422 Bowman Byrd Road Switch
CountyWilbarger
StateTX
Voltage345 kV
Capacity438.8 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-04-30
Source datasetlarge

Additional filed fields

Interconnecting EntityEastern Trail Solar Center, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete44530
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.