Substation Scout

Poco Trail Solar

ERCOT queue ID 23INR0273

Poco Trail Solar (23INR0273) is listed in the ERCOT interconnection queue as a 438.8 MW solar project in Wilbarger County, TX. The filing names Tap Riley - Bowman Byrd Road Switch as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 2, 2029. It records the screening study as complete on November 30, 2021.

Queue ID23INR0273
Project namePoco Trail Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Riley - Bowman Byrd Road Switch
Point of interconnectionTap 345kV 6101 Riley - 1422 Bowman Byrd Road Switch
CountyWilbarger
StateTX
Voltage345 kV
Capacity438.8 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2029-04-02
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Wilbarger, TX: 24 requests in the ERCOT queue, 21 active totaling 8,450.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityEastern Trail Solar Center, LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Screening study complete2021-11-30
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first