Substation Scout

Baker Branch Solar

ERCOT queue ID 23INR0026

Baker Branch Solar (23INR0026) is listed in the ERCOT interconnection queue as a 469.4 MW solar project in Lamar County, TX. The filing names tap Paris - Valley as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 30, 2026. It records the screening study as complete on June 4, 2020, the full interconnection study as approved on October 30, 2023 and the interconnection agreement as signed on February 14, 2022.

Queue ID23INR0026
Project nameBaker Branch Solar
Status (as published)SS Completed, FIS Completed, IA
Substationtap Paris - Valley
Point of interconnectiontap 345kV 1692 Paris - 1690 Valley
CountyLamar
StateTX
Voltage345 kV
Capacity469.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2026-12-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityMockingbird Solar Center, LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2022-02-14
Screening study complete2020-06-04
Full interconnection study approved2023-10-30
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first