Sierra Madre Solar
ERCOT queue ID 23INR0006
Sierra Madre Solar (23INR0006) is listed in the ERCOT interconnection queue as a 255.2 MW solar project in Zapata County, TX. The filing names tap Del Sol - Cenizo as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 1, 2027. It records the screening study as complete on April 8, 2020.
| Queue ID | 23INR0006 |
|---|---|
| Project name | Sierra Madre Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | tap Del Sol - Cenizo |
| Point of interconnection | tap 345kV 80307 Del Sol - 80225 Cenizo |
| County | Zapata |
| State | TX |
| Voltage | 345 kV |
| Capacity | 255.2 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Zapata, TX: 28 requests in the ERCOT queue, 27 active totaling 6,291.1 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Sierra Madre Solar LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2020-04-08 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.