Substation Scout

Sierra Madre Solar

ERCOT queue ID 23INR0006

Sierra Madre Solar (23INR0006) is listed in the ERCOT interconnection queue as a 255.2 MW solar project in Zapata County, TX. The filing names tap Del Sol - Cenizo as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 1, 2027. It records the screening study as complete on April 8, 2020.

Queue ID23INR0006
Project nameSierra Madre Solar
Status (as published)SS Completed, FIS Started, No IA
Substationtap Del Sol - Cenizo
Point of interconnectiontap 345kV 80307 Del Sol - 80225 Cenizo
CountyZapata
StateTX
Voltage345 kV
Capacity255.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-12-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Zapata, TX: 28 requests in the ERCOT queue, 27 active totaling 6,291.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySierra Madre Solar LLC
CDR reporting zoneSOUTH
Fuel codeSOL
Technology codePV
Screening study complete2020-04-08
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first