Aquilla Lake 3 Wind (22INR0499) is listed in the ERCOT interconnection queue as a 297.4 MW wind project in Hill County, TX. The filing names tap Kopperl to Navarro as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of November 20, 2026. It records the screening study as complete on May 28, 2021, the full interconnection study as approved on September 10, 2025 and the interconnection agreement as signed on January 24, 2024.

Queue ID22INR0499
Project nameAquilla Lake 3 Wind
Status (as published)SS Completed, FIS Completed, IA
Substationtap Kopperl to Navarro
Point of interconnectiontap 345 kV 68040 Kopperl to 68091 Navarro
CountyHill
StateTX
Voltage345 kV
Capacity297.4 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2026-11-20
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Hill, TX: 27 requests in the ERCOT queue, 23 active totaling 7,894.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityAquilla Lake 3 Wind
CDR reporting zoneNORTH
Fuel codeWIN
Technology codeWT
Interconnection agreement signed2024-01-24
Screening study complete2021-05-28
Full interconnection study approved2025-09-10
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first