Substation Scout

Bowstring BESS

ERCOT queue ID 22INR0443

Bowstring BESS (22INR0443) is listed in the ERCOT interconnection queue as a 155 MW battery project in San Patricio County, TX. The filing names WHITEPT4A - RINCON4A as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of September 18, 2028. It records the screening study as complete on February 9, 2021, the full interconnection study as approved on May 30, 2023 and the interconnection agreement as signed on September 9, 2025.

Queue ID22INR0443
Project nameBowstring BESS
Status (as published)SS Completed, FIS Completed, IA
SubstationWHITEPT4A - RINCON4A
Point of interconnection138kV 8961 WHITEPT4A - 8418 RINCON4A
CountySan Patricio
StateTX
Voltage138 kV
Capacity155 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-09-18
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

San Patricio, TX: 28 requests in the ERCOT queue, 27 active totaling 6,857.5 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityLongbow Energy Storage, LLC
CDR reporting zoneCOASTAL
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2025-09-09
Screening study complete2021-02-09
Full interconnection study approved2023-05-30
Air permitNot Required
Water availability2025-09-23

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.