Sandow Solar

ERCOT queue ID 22INR0350

Sandow Solar (22INR0350) is listed in the ERCOT interconnection queue as a 287.2 MW solar project in Milam County, TX. The filing names tap one Austrop - Sandow line as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of June 1, 2028. It records the screening study as complete on February 8, 2021 and the full interconnection study as approved on July 18, 2024.

Queue ID22INR0350
Project nameSandow Solar
Status (as published)SS Completed, FIS Completed, No IA
Substationtap one Austrop - Sandow line
Point of interconnectiontap one 345kV 7040 Austrop - 13429 Sandow line
CountyMilam
StateTX
Voltage345 kV
Capacity287.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-06-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Milam, TX: 35 requests in the ERCOT queue, 30 active totaling 8,525.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySandow Lakes Ranch Solar I, LLC
CDR reporting zoneSOUTH
Fuel codeSOL
Technology codePV
Screening study complete2021-02-08
Full interconnection study approved2024-07-18
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first