Fortuna Wind

ERCOT queue ID 22INR0301

Fortuna Wind (22INR0301) is listed in the ERCOT interconnection queue as a 295.3 MW wind project in Jack County, TX. The filing names Tap Jacksboro - WKrum as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of March 31, 2029. It records the screening study as complete on May 27, 2020, the full interconnection study as approved on May 9, 2024 and the interconnection agreement as signed on August 8, 2024.

Queue ID22INR0301
Project nameFortuna Wind
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Jacksboro - WKrum
Point of interconnectionTap 345kV 1429 Jacksboro - 1730 WKrum
CountyJack
StateTX
Voltage345 kV
Capacity295.3 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2029-03-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Jack, TX: 18 requests in the ERCOT queue, 17 active totaling 7,978.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityRWE Renewables Development, LLC
CDR reporting zoneNORTH
Fuel codeWIN
Technology codeWT
Interconnection agreement signed2024-08-08
Screening study complete2020-05-27
Full interconnection study approved2024-05-09
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.