Adamstown Solar
ERCOT queue ID 21INR0210
Adamstown Solar (21INR0210) is listed in the ERCOT interconnection queue as a 250.9 MW solar project in Wilbarger County, TX. The filing names tap West Krum - Riley Ckt 2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of August 31, 2027. It records the screening study as complete on February 4, 2019, the full interconnection study as approved on February 25, 2026 and the interconnection agreement as signed on December 4, 2024.
| Queue ID | 21INR0210 |
|---|---|
| Project name | Adamstown Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | tap West Krum - Riley Ckt 2 |
| Point of interconnection | tap 345kV 1730 West Krum - 6111 Riley Ckt 2 |
| County | Wilbarger |
| State | TX |
| Voltage | 345 kV |
| Capacity | 250.9 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-08-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Wilbarger, TX: 24 requests in the ERCOT queue, 21 active totaling 8,450.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Adams Creek Solar Project, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2024-12-04 |
| Screening study complete | 2019-02-04 |
| Full interconnection study approved | 2026-02-25 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.