Peyton Creek Wind II
ERCOT queue ID 20INR0155
Peyton Creek Wind II (20INR0155) is listed in the ERCOT interconnection queue as a 241.2 MW wind project in Matagorda County, TX. The filing names Refuge as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 31, 2026. It records the screening study as complete on November 2, 2018, the full interconnection study as approved on June 25, 2024 and the interconnection agreement as signed on April 29, 2026.
| Queue ID | 20INR0155 |
|---|---|
| Project name | Peyton Creek Wind II |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Refuge |
| Point of interconnection | 42400 Refuge 345kV |
| County | Matagorda |
| State | TX |
| Voltage | 345 kV |
| Capacity | 241.2 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2026-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Matagorda, TX: 30 requests in the ERCOT queue, 23 active totaling 5,513.1 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | RWE Renewables Development, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | WIN |
| Technology code | WT |
| Interconnection agreement signed | 2026-04-29 |
| Screening study complete | 2018-11-02 |
| Full interconnection study approved | 2024-06-25 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.