Substation Scout

Fagus Solar Park 1 SLF

ERCOT queue ID 20INR0091

Queue ID20INR0091
Project nameFagus Solar Park 1 SLF
Status (as published)SS Completed, FIS Completed, IA
SubstationTesla
Point of interconnection60501 Tesla 345kV
CountyChildress
StateTX
Voltage345 kV
Capacity166.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2026-05-20
Source datasetlarge

Additional filed fields

Interconnecting EntityExcel Advantage Services, LLC dba Misae Solar Park II
Cdr ZonePANHANDLE
Fuel CodeSOL
Technology CodePV
Ia Signed43517
Screening Study Complete43287
Fis Approved45349
Air PermitNot Required
Water AvailabilityNot Required