Grandfalls Solar
ERCOT queue ID 19INR0002
Grandfalls Solar (19INR0002) is listed in the ERCOT interconnection queue as a 175.6 MW solar project in Upton County, TX. The filing names 842 King Mountain Station as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of November 25, 2026. It records the screening study as complete on June 6, 2016, the full interconnection study as approved on December 17, 2025 and the interconnection agreement as signed on January 23, 2025.
| Queue ID | 19INR0002 |
|---|---|
| Project name | Grandfalls Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | 842 King Mountain Station |
| Point of interconnection | 842 King Mountain Station 345kV |
| County | Upton |
| State | TX |
| Voltage | 345 kV |
| Capacity | 175.6 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2026-11-25 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Upton, TX: 22 requests in the ERCOT queue, 18 active totaling 5,611.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | King Mountain Solar, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2025-01-23 |
| Screening study complete | 2016-06-06 |
| Full interconnection study approved | 2025-12-17 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.