Substation Scout

Coyote Wind

ERCOT queue ID 17INR0027b

Coyote Wind (17INR0027b) is listed in the ERCOT interconnection queue as a 242.6 MW wind project in Scurry County, TX. The filing names Dermott as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of August 28, 2026. It records the screening study as complete on May 22, 2015, the full interconnection study as approved on January 31, 2020 and the interconnection agreement as signed on August 9, 2016.

Queue ID17INR0027b
Project nameCoyote Wind
Status (as published)SS Completed, FIS Completed, IA
SubstationDermott
Point of interconnection11305 Dermott 345kV
CountyScurry
StateTX
Voltage345 kV
Capacity242.6 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2026-08-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Scurry, TX: 23 requests in the ERCOT queue, 17 active totaling 5,057.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityCoyote Wind
CDR reporting zoneWEST
Fuel codeWIN
Technology codeWT
Interconnection agreement signed2016-08-09
Screening study complete2015-05-22
Full interconnection study approved2020-01-31
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.