Priddy Wind
ERCOT queue ID 16INR0085
| Queue ID | 16INR0085 |
|---|---|
| Project name | Priddy Wind |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | tap Brown – Killeen |
| Point of interconnection | tap 345kV 1444 Brown – 3422 Killeen |
| County | Mills |
| State | TX |
| Voltage | 345 kV |
| Capacity | 302.4 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2026-12-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | ENGIE North America |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | WIN |
| Technology Code | WT |
| Ia Signed | 44056 |
| Screening Study Complete | 42045 |
| Fis Approved | 44316 |
| Air Permit | Not Required |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.