Waller, TX interconnection queue

5 active projects totalling 924.1 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

5active projects
924.1active MW
6total filed
Queue IDProjectkVMWResourceStatus
27INR0235 Ochoa Energy Storage II n/r 516.6 Battery Cancelled
26INR0425 Twinwood Solar 1 138 358.1 Solar SS Completed, FIS Started, IA
26INR0243 Caladium BESS 69 201.3 Battery SS Completed, FIS Started, No IA
24INR0461 Augie BESS 138 200.8 Battery SS Completed, FIS Completed, No IA
26INR0426 Maderagemela BESS1 138 154 Battery SS Completed, FIS Started, IA
26INR0773 Seaway BESS 138 9.9 Battery In Queue

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.