Comal, TX interconnection queue
3 active projects totalling 867 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).
3active projects
867active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0242 | Enfinity Redbud Storage | 345 | 516.1 | Battery | SS Completed, FIS Started, No IA |
| 28INR0436 | Englehardt BESS | n/r | 200.5 | Battery | SS Completed, FIS Started, No IA |
| 30INR0112 | Short River BESS | 138 | 150.4 | Battery | SS Started, FIS Started, No IA |
| 23INR0152 | Madrone Energy Storage | n/r | 102.5 | Battery | Inactive |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.