Carson, TX interconnection queue

4 active projects totalling 1,618.2 MW in the ERCOT queue, plus 2 with terminal status (shown greyed).

4active projects
1,618.2active MW
6total filed
Queue IDProjectkVMWResourceStatus
28INR0033 Corvette Wind n/r 1,200 Wind Inactive
27INR0140 Kingsmill Wind SLF 345 606.3 Wind SS Completed, FIS Started, IA
27INR0022 Panhandle Flagship Solar 1 345 439.4 Solar SS Completed, FIS Started, IA
27INR0025 Panhandle Flagship Storage 345 371.7 Battery SS Completed, FIS Started, IA
23INR0283 Kota Battery 345 200.8 Battery SS Completed, FIS Started, No IA
17INR0036 Grandview 4 Phase A Wind n/r 200.5 Wind Inactive

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.