4 active projects totalling 879.4 MW in the ERCOT queue.

4active projects
879.4active MW
4total filed
Queue IDProjectkVMWResourceStatus
28INR0059 Verily Solar (FKA Cuello De Cuero Solar) 345 261 Solar SS Completed, FIS Started, No IA
27INR0400 Reforzar BESS 1 345 207.6 Battery SS Completed, FIS Completed, No IA
27INR0401 Reforzar Bess 2 345 207.6 Battery SS Completed, FIS Started, No IA
23INR0087 Kinenos Solar 345 203.2 Solar SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.