Substation Scout

Line tap into BPA Harney-Brasada line substation interconnection queue

1 active project totalling 20 MW in the BPA queue, plus 1 with terminal status (shown greyed).

1active projects
20active MW
2total filed
Queue IDProjectkVMWResourceStatus
G0536 Not reported 115 20 Solar WITHDRAWN
G0537 Not reported 115 20 Solar STUDY

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.