Smith Creek
BPA queue ID G0511
| Queue ID | G0511 |
|---|---|
| Project name | Smith Creek |
| Status (as published) | ENERGIZED |
| Substation | BPA's Bonners Ferry Substation |
| Point of interconnection | BPA's Bonners Ferry Substation |
| County | Boundary |
| State | ID |
| Voltage | Not reported |
| Capacity | 39 MW |
| Resource (as published) | Water/Hydro |
| Resource category | Hydro (normalised for filtering) |
| Target commercial operation | 1987-04-10 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Eugene Water & Electric Board |
|---|---|
| Connection Type | GI |
| Interconnection Type | NRIS |
| Poi | BPA's Bonners Ferry Substation |
| Generator Type | Hydro |
| Fuel Source | Water |
| Nameplate Mw Total | 39 |
| Max Summer Mw | 39 |
| Max Winter Mw | 39 |
| Reason Not Completed | . |
| Comments | Existing hydro generation currently in full operation. |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.