Carty CCCT

BPA queue ID G0457

Queue IDG0457
Project nameCarty CCCT
Status (as published)ENERGIZED
SubstationSlatt substation.
Point of interconnectionSlatt substation.
CountyMorrow
StateOR
VoltageNot reported
Capacity36 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2015-05-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorPortland General Electric Company
Connection TypeGI
Interconnection TypeNRIS
PoiSlatt substation.
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total36
Max Summer Mw36
Max Winter Mw36
Reason Not Completed.
CommentsIncrement to Interconnection Request G0380; Expected Synch date 11/15/15